Projects Complete

Denver Public Schools - Manual High School - PP8094

Manual High School - Artificial Turf
Andrew Amador - DPS Project Manager
Work Completed: August 2010
DPS Parent Project 8094
Construction Cost: $1.4M
*Replace existing grass football field, asphalt track, & irrigation system. Modifications included new field drainage system, new artificial turf football field, synthetic track and upgrades to the existing structures.

Brown Elementary, CEC Middle College, Cheltenham Elementary & Valdez Elementary School - General Renovations
Andrew Amador - DPS Project Manager
Work Completed: August 2010
DPS Parent Project 8035
Construction Cost: $688,958.00
*Brown Elementary - Full Carpet Replacement, ADA Upgrades and Full parking lot replacement.
* CEC Middle College - Replace seamless floor at culinary arts kitchen
*Cheltenham Elementary - Full window replacement of entire school and full replacement of the irrigation system to a IBAS smart irrigation controller.

Denver Public Schools - Asphalt Paving Project - PP8161

Denver Public Schools Service Building Upgrades - Asphalt Parking Lot upgrades, ADA Upgrades & Concrete Service Drive upgrades.
Andrew Amador - DPS Project Manager
Work Completed: August 2010
DPS Parent Project 8161
Construction Cost: $646,645.00
*Service Building Upper & Middle Lot - Replace existing asphalt concrete parking lots and replace service drive with concrete & valley pan for drainage. Also reconstructructed ADA ramp to the main entrance of the building to become code compliant.
* Service Building Lower Lot - Replace existing asphalt concrete.
*Hamilton Middle School - Replace existing asphalt concrete parking lots.
*Holm Middle School - Replace existing asphalt concrete parking lots.

Denver Public Schools - Bleacher Replacement Project - PP8403

East, West, Thomas Jefferson, Montbello & JFK's High Schools
Main Gymnasium Telescoping Bleacher Replacement
Andrew Amador - DPS Project Manager
Work Completed: August 2011
DPS Parent Project 8403
Construction Cost: $738,096.00
*Replace the existing wood bleachers at the five high schools with new motorized telescoping bleachers simultaneously during the summer.

Cowell Elementary & Knapp Middle School - Window Replacement
Andrew Amador - DPS Project Manager
Work Completed: August 2011
DPS Parent Project 8523
Construction Cost: $461,519.00
*Cowell Elementary - Full window replacement of entire school.
* Knapp Middle School - Added security window grilles.

Valverde Elementary & Kepner Middle School - General Renovations & Full Window Replacement
Andrew Amador - DPS Project Manager
Work Completed: August 2011
DPS Parent Project 8161
Construction Cost: $1.88 M
*Valverde Elementary - Various ADA upgrades including an elevator, plumbing fixture replacement & various door hardware upgrades.
* Kepner Middle School - Full window replacement, plumbing fixture replacement, install new roof access ladders on exterior of the building & entire school door hardware upgrades.

Greenlee Elementary & Columbian Elementary - Markerboards
Andrew Amador - Architect & DPS Project Manager
Work Completed: August 2011
DPS Parent Project 8445
Construction Cost: $24,750.00
*Greenlee Elementary - Replace chalkboards with magnetic whiteboards.
*Columbian Elementary - Replace chalkboards with magnetic whiteboards.

Goldrick Elementary & Godsman Elementary - Roof Replacement
Andrew Amador - DPS Project Manager
Work Completed: August 2011
DPS Parent Project 8112 & 8468
Construction Cost: $453,513.00
*Goldrick Elementary - Replace various roof decks with a built-up roofing system and installed new roof access point.
*Godsman Elementary - Replace various roof decks with a built up roofing system.

Knapp Elementary School – Boiler Replacement
Knapp Elementary School – Boilers
Andrew Amador - DPS Project Manager
Work Completed: August 2012
DPS Parent Project 8435
Construction Cost: $354,325.00
*Replace existing boilers with new controls and high efficiency boilers.

Golrdick, Knapp, Munroe & Newlon Elementary Schools - General Renovations
Andrew Amador - DPS Project Manager
Work Completed: August 2012
DPS Parent Project 8111
Construction Cost: $482,707.00
*Goldrick Elementary - Full Paint Restoration & ADA Upgrades.
* Knapp Elementary – ADA compliance & Learning Landscape modifications.
*Munroe Elementary – Shell Masonry repair, exterior and interior paint renovation, built-up roofing replacement of limited roofing decks and ADA compliance.
*Newlon Elementary – ADA compliance consisting of the relocation of the main computer lab within the school.

Denver Public Schools - Balarat Outdoor Education Center - PP8412Balarat Outdoor Education Facilities – General Renovations & New Outbuilding
Andrew Amador - DPS Project Manager
Work Completed: August 2012
DPS Parent Project 8412
Construction Cost: $264,218.00
*Replace Built-Up Roofing of existing structures, ADA compliance & New Out Building.

Beach Court, Edison & Valdez Schools - General Renovations
Edison Elementary School - Window Replacement
Andrew Amador - DPS Project Manager
Work Completed: August 2012
DPS Parent Project 8028
Construction Cost: $933,618.00
*Beach Court – Finish restoration of carpet, ADA Upgrades and new school interior signage.
* Edison – Full Window Replacement & ADA compliance.
*Valdez Elementary – Finish restoration of all seamless floors to tile.

Update Denver Public Schools Design and Construction Standards
September 30, 2009
Andrew Amador - DPS Project Manager/Coordinator
*Updated the Design & Construction Standard Specifications for architects use in the 2008 G.O.B Projects and future DPS projects.
*Updated the Design & Construction Standard Drawings for architects use in the 2008 G.O.B Projects & future DPS projects.
*Developed a secure website to host both the updated Design & Construction Standard Specifications and all DPS Standard Drawings.